bannerd


7.08 - Maturity of Life Cycle Products at Milestone Reviews

1. Introduction and Chart

This chart summarizes current guidance approved by the NASA Office of the Chief Engineer (OCE) for software engineering life cycle products and their maturity level at the various software project life cycle reviews.   This chart serves as guidance only and NASA Center procedures should take precedence for projects at those Centers.

The chart was constructed using the software engineering products from NPR 7150.2 083, the project life cycle reviews from NPR 7123.1 041, previous work from the NASA Software Working Group to map products to life cycle reviews, and additional information gathered from these NPRs, NPR 7120.5 082, and individual NASA Center procedures.  Draft versions of the chart were reviewed by the NASA Software Working Group resulting in this chart which represents the current consensus guidance from this collection, collation, and review process.

The following maturity definitions from NPR 7120.5 are used in this table:

a. "Preliminary" is the documentation of information as it stabilizes but before it goes under configuration control. It is the initial development leading to a baseline.
Some products will remain in a preliminary state for multiple life cycle reviews. The initial preliminary version is likely to be updated at subsequent life cycle reviews but remains preliminary until baseline.
b. "Baseline" indicates putting the product under configuration control to track, approve, and communicate changes to the team and any relevant stakeholders. The expectation on products labeled "baseline" is that they will be at least final drafts going into the designated life cycle review and baselined coming out of the life cycle review. Updates to baselined documents require the same formal approval process as the original baseline.
c. "Update" is applied to products that are expected to evolve as the formulation and implementation processes evolve. Only expected updates are indicated.
However, any document may be updated, as needed. Updates to baselined documents require the same formal approval process as the original baseline.

NPR 7150.2 includes life cycle products that are not included in the chart and life cycle reviews that are also not represented in the chart.  

Links are provided where "Minimum Content" document topics are available. 

7150.2 Software Life Cycle Products

MCRSRRSwRRMDRSDRPDRCDRSIRTRRSARORR

Software Development Plan (SDP) / Software Management Plan (SMP) - 5.08 - SDP-SMP - Software Development - Management Plan

 

P

P

P

 B

 

U





NPR 7150.2 Requirements mapping table for the software engineering requirements see Topic 7.16 - Appendix C. Requirements Mapping and Compliance Matrix 


P

P

P

B

U

U





Software Schedule

D

P

P

U

U

B

U





Software Cost Estimate

D

P

P

U

U

B

U





Software Configuration Management Plan (SCMP)
- 5.06 - SCMP - Software Configuration Management Plan


P

P

P

P 

B

U





Software Test Plans
- 5.10 - STP - Software Test Plan






P

B

U

U



Software Test Procedures
- 5.14 - Test - Software Test Procedures







P

 

B



Software Test Reports
- 5.11 - STR - Software Test Report










F


Software Maintenance Plan
- 5.04 - Maint - Software Maintenance Plan

  

 
   

 D

 P

 P

 B

 U

Software Requirements Specification (SRS)
- 5.09 - SRS - Software Requirements Specification

 

P

P

P 

 P

B

U

 

U



Requirements on OTS s/w

 

P

P

P 

 P

B

U





Software Data Dictionary
- 5.07 - SDD - Software Data Dictionary



P

P

P 

P

B





Software Design Description (Architectural Design)
- 5.13 - SwDD - Software Design Description





 

B

U

 

U



Software Design Description (Detailed Design)
- 5.13 - SwDD - Software Design Description





 

P

B

 

U



Interface Design Description
- 5.02 - IDD - Interface Design Description





 

P

B

 

U



Software User's Manual (SUM)
- 5.12 - SUM - Software User Manual











B

Records of Continuous Risk Management

P

U

U

U

U

U

U

 

 U

U


Measurement Analysis Results
- 5.05 - Metrics - Software Metrics Report



P

P

P 

X

X





Operational Concepts (part of "Mission Operations Concept" or separate)

 

P

P

U

 U

B

U





Record of trade-off criteria & assessment (make/buy decision)





 

X

X





Acceptance Criteria and Conditions




 

 

P

B





Software Assurance and Software Safety (from NASA-STD-8739.8)

MCR

SRR

SwRRMDRSDRPDRCDRSIRTRRSARORR
Products










Software Assurance and Software Safety Plan(s)
- 8.51 - Software Assurance Plan

D
DPBUU



Cost estimate for the project’s Software Assurance and Software Safety support.DPPBUUU



Requirements mapping table for the software assurance and software safety standard requirements
DDPBUU



IV&V Project Execution Plan (if required)
- 8.53 - IV&V Project Execution Plan

PPPPBUUUU
IV&V Project risk assessment  (if required)
PPPBUUUU

Software Assurance schedule
PPPBUU



Software Assurance Product Acceptance Criteria and Conditions

PPPPX



Software Assurance Requirement Analysis
- 8.54 - Software Requirements Analysis




PXUUU

Software Assurance and Software Safety hazard analysis
- 8.58 - Software Safety and Hazard Analysis


PPPXUUU

Software Assurance safety analysis
- 8.58 - Software Safety and Hazard Analysis


PPPPXUUU
Software Assurance design analysis
- 8.55 - Software Design Analysis




PPXUUU
Software source code quality analysis
- 8.56 - Source Code Quality Analysis






PX


Software Assurance test analysis
- 8.57 - Testing Analysis






PPXU
Software static code assessments





PPX

Analysis showing software code coverage percentage for safety-critical code







X

Analysis showing software code complexity for safety-critical code







X

Ongoing activities










Software Process Root Cause Analysis results




UUUUU
Software risks, findings, or known issues 
UUUUUUUUUU
Evaluation of software changes



UUUUUUU
Software Assurance status reports, including Software Assurance metric analysis
- 8.52 - Software Assurance Status Reports


PPSPPSPPSPPSPPSPPSPPSPPSPPS
Participation in Software Peer reviews

PPSPPSPPSPPSPPSPPSPPSPPSPPS
Software Assurance process audits
- 8.59 - Audit Reports


PPSPPSPPSPPSPPSPPSPPSPPSPPS
Software test witnessing





PPSPPSPPSPPSPPS
Software Assurance participation in milestone product reviews
PPSPPSPPSPPSPPSPPSPPSPPSPPSPPS

Legends

Maturity Types 

F = Final,  D = Draft,  P = Preliminary,  B = Baseline,  U = Updated/Updated as required,  X = assume complete (final),
PPS = Per Project Schedule or Software Assurance Schedule as appropriate


Review Types

MCR = Mission Concept Review,SRR = System Requirements ReviewSwRR = Software Requirements Review
MDR = Mission Definition ReviewSDR = System Definition ReviewPDR = Preliminary Design Review
CDR = Critical Design ReviewSIR = System Integration ReviewTRR = Test Readiness Review
SAR = System Acceptance ReviewORR = Operational Readiness Review

See also SWE-024 - Plan Tracking, 7.09 - Entrance and Exit Criteria, 8.09 - Software Safety Analysis


1.1 Additional Guidance

Links to Additional Guidance materials for this subject have been compiled in the Relevant Links table. Click here to see the Additional Guidance tab in the Resources tab.

2. References

2.1 References



2.2 Tools


Tools to aid in compliance with this SWE, if any, may be found in the Tools Library in the NASA Engineering Network (NEN). 

NASA users find this in the Tools Library in the Software Processes Across NASA (SPAN) site of the Software Engineering Community in NEN. 

The list is informational only and does not represent an “approved tool list”, nor does it represent an endorsement of any particular tool.  The purpose is to provide examples of tools being used across the Agency and to help projects and centers decide what tools to consider.

2.3 Additional Guidance

Additional guidance related to this requirement may be found in the following materials in this Handbook:

2.4 Center Process Asset Libraries

SPAN - Software Processes Across NASA
SPAN contains links to Center managed Process Asset Libraries. Consult these Process Asset Libraries (PALs) for Center-specific guidance including processes, forms, checklists, training, and templates related to Software Development. See SPAN in the Software Engineering Community of NEN. Available to NASA only. https://nen.nasa.gov/web/software/wiki  197

See the following link(s) in SPAN for process assets from contributing Centers (NASA Only). 

SPAN Links



3. Lessons Learned

3.1 NASA Lessons Learned

No Lessons Learned have currently been identified for this requirement.

3.2 Other Lessons Learned

No other Lessons Learned have currently been identified for this requirement.

  • No labels