4.2.4 The project manager shall perform a software architecture review on the following categories of projects:

    1. Category 1 Projects as defined in NPR 7120.5.
    2. Category 2 Projects as defined in NPR 7120.5 that have Class A or Class B payload risk classification per NPR 8705.4.
Difference between B and C

No change

C

4.2.4 The project manager shall perform a software architecture review on the following categories of projects:

    1. Category 1 Projects as defined in NPR 7120.5.
    2. Category 2 Projects as defined in NPR 7120.5 that have Class A or Class B payload risk classification per NPR 8705.4.

Difference between C and DNo change
D

4.2.4 The project manager shall perform a software architecture review on the following categories of projects: 

a. Category 1 Projects as defined in NPR 7120.5.
b. Category 2 Projects as defined in NPR 7120.5, that have Class A or Class B payload risk classification per NPR 8705.4.