SWE-121 - Last used in rev NPR 7150.2D
Rev | SWE Statement |
---|---|
A | 6.1.2 Where approved, the requesting Center or project shall document the approved alternate requirement in the procedure controlling the development, acquisition, and/ or deployment of the affected software. |
Difference between A and B | No change |
B | 2.2.4 Where approved, the project manager shall document and reflect the tailored requirement in the plans or procedures controlling the development, acquisition, and/or deployment of the affected software |
Difference between B and C | Changed "and/or" to "and". |
C | 3.1.12 Where approved, the project manager shall document and reflect the tailored requirement in the plans or procedures controlling the development, acquisition, and deployment of the affected software. |
Difference between C and D | No change |
D | 3.1.12 Where approved, the project manager shall document and reflect the tailored requirement in the plans or procedures controlling the development, acquisition, and deployment of the affected software. |