SWE-051 - Last used in rev NPR 7150.2D
Rev | SWE Statement |
---|---|
A | 3.1.1.3 The project shall perform software requirements analysis based on flowed down and derived requirements from the top-level systems engineering requirements and the hardware specifications and design. |
Difference between A and B | No change |
B | 4.1.2.2 The project manager shall perform software requirements analysis based on flowed down and derived requirements from the top-level systems engineering requirements and the hardware specifications and design. |
Difference between B and C | Added requirement to perform software requirements analysis based on safety and reliability analyses. |
C | 4.1.3 The project manager shall perform software requirements analysis based on flowed-down and derived requirements from the top-level systems engineering requirements, safety and reliability analyses, and the hardware specifications and design. |
Difference between C and D | No change |
D | 4.1.3 The project manager shall perform software requirements analysis based on flowed down and derived requirements from the top-level systems engineering requirements, safety and reliability analyses, and the hardware specifications and design. |