Rev | SWE Statement |
---|---|
A | 2.6.1.1 The project shall require the software supplier(s) to provide insight into software development and test activities; at a minimum the following activities are required: monitoring integration, review of the verification adequacy, review of trade study data and results, auditing the software development process, participation in software reviews and systems and software technical interchange meetings. |
Difference between A and B | No change |
B | 3.12.8 The project manager shall require the software supplier(s) to provide insight into software development and test activities; at a minimum, the software supplier(s) will be required to allow the project manager or designate to:
|
Difference between B and C | Changed "supplier(s)" to "developer(s)"; |
C | 3.1.8 The project manager shall require the software developer(s) to periodically report status and provide insight into software development and test activities; at a minimum, the software developer(s) will be required to allow the project manager and software assurance personnel to:
|
Difference between C and D | No change |
D | 3.1.8 The project manager shall require the software developer(s) to periodically report status and provide insight into software development and test activities; at a minimum, the software developer(s) will be required to allow the project manager and software assurance personnel to:
|