5.1.2.1 The Software Configuration Management Plan shall contain: [SWE-103] a. The project organization(s). NPR 7150.2, NASA Software Engineering Requirements, does not include any notes for this requirement. Class B, Class B Safety Critical, and Classes C through E Safety Critical are labeled, "P (Center) + SO." This means that this requirement applies to the safety-critical aspects of the software and that an approved Center-defined process that meets a non-empty subset of the full requirement can be used to achieve this requirement. Class C Not Safety Critical, Class D Not Safety Critical, and Class G are labeled with "P (Center)." This means that an approved Center-defined process that meets a non-empty subset of the full requirement can be used to achieve this requirement. Class A_SC A_NSC B_SC B_NSC C_SC C_NSC D_SC D_NSC E_SC E_NSC F G H Applicable? X X X P(C) X P(C) X P(C) Key: A_SC = Class A Software, Safety-Critical | A_NSC = Class A Software, Not Safety-Critical | ... | - Applicable | - Not Applicable Configuration management is the "process of identifying and defining the configuration items in a system, controlling the release and change of these items throughout the system life cycle, recording and reporting the status of configuration items and change requests, and verifying the completeness and correctness of configuration items." 276 This work can only be properly accomplished if there exists a plan addressing all of these activities, which has been reviewed by an appropriate set of stakeholders and tailored for a specific project's needs. The Software Configuration Management (SCM) Plan may be tailored by software classification. Goddard Space Flight Center's (GSFC's) 580-STD-077-01, Requirements for Minimum Contents of Software Documents, 090 provides one suggestion for tailoring an SCM Plan based on the required contents and the classification of the software being developed. When creating an SCM Plan, using a template ensures consistent plans for all projects at a Center. Consider the following guidance, listed by the required elements shown in the NPR 7150.2 text for this SWE, to ensure that all the required content is properly addressed and tailored for the project: Project organization(s) Consider the following when writing the project organization section of the SCM Plan: Responsibilities The responsibilities of the SCM organization include: References to SCM policies and directives This section of the SCM Plan needs to list any specific SCM policies and directives that apply to or impact SCM for the project. Those policies and directives may be named in a reference section of the plan, so referring to that section may be appropriate. However, the impact of those policies and directives on SCM for the project is described here. Consider: All functions and tasks required to manage the configuration of the software This section of the plan describes configuration identification, configuration control, status accounting, and configuration audits and reviews. Guidance for each of these topics is found in the related requirements (see table below) in this Handbook. This section of the SCM Plan describes how each of these SCM functions will be performed. Consider using a separate subsection for each of the four functions. As appropriate for the project, the following highlights are to be included but are not to be considered the only items to document: If the project uses data management in addition to SCM, those activities are described in this section of the SCM Plan, including: Schedule This section of the plan includes information necessary to describe "the sequence and coordination for the identified activities and for all events affecting the plan's implementation" (NPR 7150.2, section 5.1.2.1.e). The SCM schedule needs to coordinate with the project schedule, and this part of the SCM Plan shows that coordination. Graphics (timelines) may be useful. Typically, configuration items are uncontrolled until some gate or milestone is reached, at which time they are required to be placed under configuration control. Each configuration item or group of items may have its own gate. Because those gates can be points in the project timeline, consider describing those gates in this section. Also consider for the SCM schedule: Resources The resources section of the SCM Plan describes the software tools, techniques, and equipment that will be used to carry out SCM for the project. References to the relevant documentation for installing and using these tools is included, as well as the configuration controls for each tool. Typical resources include: Plan maintenance The maintenance section provides information such as: Release management and delivery NASA-GB-8719.13, NASA Software Safety Guidebook, 276 states: "Configuration Management should act as the sole distributor of media and documentation for all system tests and for delivery to [sub]system integration and testing. Pulling the latest program off the developer's machine is not a good idea. One aspect of system testing is repeatability, which can only be assured if the software under test comes from a known, and fixed, source." 276 The release management and delivery activity is described in this portion of the SCM Plan (see SWE-085 for release management guidance), including formal control of the build, release, and delivery of software products and documentation. Consult Center Process Asset Libraries (PALs) for Center-specific guidance, templates, and resources related to the content of the configuration management plan. Additional guidance related to the content of the configuration management plan may be found in the following related requirements in this Handbook: Configuration management activities are based on risk, so projects designated small by size of the team or budget need to ensure that their Software Configuration Management (SCM) Plans include all the required content, while including only those processes and the associated structure necessary to manage project risk. This might mean planning to use simpler tools or fewer personnel (filling multiple roles) to carry out the SCM processes. It could also mean planning to use a single tool for multiple purposes to reduce tool management and overhead. Small projects may not require the formality of a separate SCM Plan; instead, SCM planning may be documented as a section of the project's Software Management Plan. Alternatively, one master SCM Plan may document configuration management for multiple small projects. Tools to aid in compliance with this SWE, if any, may be found in the Tools Library in the NASA Engineering Network (NEN). NASA users find this in the Tools Library in the Software Processes Across NASA (SPAN) site of the Software Engineering Community in NEN. The list is informational only and does not represent an “approved tool list”, nor does it represent an endorsement of any particular tool. The purpose is to provide examples of tools being used across the Agency and to help projects and centers decide what tools to consider. A documented lesson from the NASA Lessons Learned database notes the following: Place Flight Scripts Under Configuration Management Prior to ORT (Project attention to configuration control). Lesson Number 2476: "Project attention to the configuration control of flight scripts is likely to prevent the generation of unnecessary software iterations, improve the rigor of mission system engineering processes, and ensure consistency in the test and operations environments." 574
See edit history of this section
Post feedback on this section
1. Requirements
b. Responsibilities of the software configuration management organization.
c. References to the software configuration management policies and directives that apply to the project.
d. All functions and tasks required to manage the configuration of the software, including configuration identification, configuration control, status accounting, and
configuration audits and reviews.
e. Schedule information, which establishes the sequence and coordination for the identified activities and for all events affecting the plan's implementation.
f. Resource information, which identifies the software tools, techniques, and equipment necessary for the implementation of the activities.
g. Plan maintenance information, which identifies the activities and responsibilities necessary to ensure continued planning during the life cycle of the project.
h. Release management and delivery.1.1 Notes
1.2 Applicability Across Classes
X - Applicable with details, read above for more | P(C) - P(Center), follow center requirements or procedures2. Rationale
3. Guidance
4. Small Projects
5. Resources
5.1 Tools
6. Lessons Learned
SWE-103 - Software CM Plan
Web Resources
View this section on the websiteUnknown macro: {page-info}
"Software Configuration Management is usually performed using a tool (program). However, a file or folder needs to be maintained, to collect information that is not in electronic form. This information could include the design notes scribbled on a napkin or a fax that only exists in hard-copy. The point is to collect all pertinent information in one place. It is a good idea to catalog all the hardcopy information in the electronic SCM system, so that it can be found again when needed." 276
"Describe how the project will manage information throughout its life cycle, including the development and maintenance of an electronic program library. Explain how the project will ensure identification, control, and disposition of project records in accordance with NPD 1440.6, NASA Records Management, and NPR 1441.1, Records Retention Schedules." 082